The information presented below is based on facts presented at the Public Consultation on Thursday Jan, 6th by the representatives of Toronto Redi-Mix.

On Sunday January 9, we requested that Toronto Redi-Mix confirm or correct this information. They have said that they will respond within the next week. [ View Email Request & Response ]

Toronto Redi-Mix Site Plan

   View the Site Plan submitted by Toronto Redi-Mix (1.7 MB)

According to the proposal, Toronto Redi-Mix will use approximately 6 of the 15 acres at 207 New Toronto Street to operate the following 3 businesses:

1. Toronto Redi-Mix Concrete Batching Plant

Structures 1 portable batching plant - silo is approx. 40 feet in height
5 aggregate storage units to store gravel and sand
Months of Operation April - November (Dependant on weather conditions)
Operating Hours 6:00 am - 7:00 pm, Monday - Friday
6:00 am - 3:00 pm Saturday and Sunday
Vehicle Activity 10 Redi-Mix concrete trucks making a maximum of 3-4 trips per day per truck, filled will cement, aggregate and water mixture, used to mix and distribute the cement

1 cement truck, 2-3 trips per day.
This truck blows cement into the batching silo.

Number of vehicles required to replenish the aggregate stock has not been provided.
Photos Provided by Toronto Redi-Mix
Pictures of comparable Concrete Batching sites (Click to enlarge)


2. Draglam Road Salt storage and distribution

Structures 2 Salt Sheds constructed with 3 concrete block walls, covered with a domed tarp, on an asphalt pad
Maximum height: unknown for sure but estimated at 30 feet.
Months of Operation November - April (Dependant on weather conditions)
Operating Hours 7:00 am - 7:00 pm, 7 days per week
Open 24 hours during winter storms
Vehicle Activity 4-5 trucks to deliver salt / aggregate each day, making 3-4 round trips per day to pick up and distribute salt OR aggregate

Unspecified number of small trucks to pick up salt/aggregate

Number of vehicles required to replenish the salt stock has not been provided.
Photos Provided by Toronto Redi-Mix
Pictures of comparable Storage Shed (Click to enlarge)


3. Aggregate storage and distribution

Structures 8 aggregate storage units - up to 10 metres high
Months of Operation April - November (Dependant on weather conditions)
Operating Hours 7:00 am - 7:00 pm, 7 days per week
Vehicle Activity Same as Draglam Salt Activity.
Photos Provided by Toronto Redi-Mix
Pictures of comparable Storage Shed (Click to enlarge)

Observations:

The agreggate is piled higher than the walls of the storage bins.

Bridget Mills, Environmental Consultant representing Toronto Redi-Mix, made it clear that the storage bins will effectively contain the dust and materials ONLY if the aggregate is piled lower than the height of the walls.

Cement Batching vs. Concrete Batching

In Concrete Batching, the cement is mixed with water and aggregate in the cement mixing truck.
In Cement Batching, the cement is mixed on site in a kiln.

Truck Routes

We have been told that all trucks will travel along Kipling, Islington and New Toronto Street. There will be NO TRAFFIC along residential streets

Building without a Permit

During his opening remarks, Glenn Wellings, consultant from MHBC Planning Limited, stated that Toronto Redi-Mix

did not apply for a building permit

when constructing the salt dome (currently on the site) because they

"didn't know they needed one".



* * * * * * * * * * * * * * * * * * * * * *

Dec 1, 2004  A Stop Work order has been issued by the city of Toronto